Lightning fast factory layout change using Critical Chain Project Management. 6.5 days instead of 8 weeks. A client testimonial by Safran. [...] they then decided to change the layout of the machines to improve the flow even more, simplifying the production flow and re-organizing the production lines by product families. The target of the new layout was to help reduce lead times even further, simplifying the flow of parts, and increasing productivity…
Guillaume Brethenoux, Maintenance Manager in charge of this project used the Critical Chain Project Management Principles to challenge the initial planning of 8 weeks and eventually achieve the layout change of the shop floor in… 6.5 days!
|
|
Scooped by
Philip Marris
onto Critical Chain Project Management April 3, 6:32 AM
|
Your new post is loading...