There are TWO Lower Dolington Road Trail (LDRT) Punch Lists:
- an unofficial “Citizen’s Punch List” and
- an official FINAL PUNCHLIST prepared by Remington-Vernick Engineering (RVE), the township engineering firm
On August 29, 2023, the township released a LDR Trail project “FINAL PUNCHLIST” based on the Township Engineer's field inspection conducted on August 23, 2023. Find the official list here: https://bit.ly/Final_LDRT_Punchlist
Contractor Has Until Sept 8, 2023, to Fix 33 Lower Dolington Rd Trail Problems Identified in #NewtownPA Punch List
According to the instructions given the contractor by the Township Engineer: “All (33) items shall be performed at the expense of Associated Paving Contractors, Inc. unless otherwise noted. Work must be completed by Friday, September 8, 2023. Failure to meet this deadline may result in the assessment of Engineering and Inspection fees and/or liquidated damages as outlined in the contract documents. Our firm [RVE] will schedule a close-out inspection after the list has been completed. The Township, and its representing agencies, also reserve the right to review the project site prior to the close-out inspection regarding completion of current items and the documenting of additional items.”
Contents
- First, Some History
- Official Punch List
- Citizen’s Punch List
- Signs obscured by trees
- Trees planted under power lines
- Aesthetically unpleasing metal guiderails set too close to travel lane
- More
- More Issues Identified By Citizens
- Loose Guardrail Attenuator
- Poor Installation of Guardrail Posts
- Guardrail Posts Too Close Together
- Standing Water on ADA Ramp
- Loose Stones Could Be Hazard to Motorists
- Other Concerns
- UnSafe/ADA Access to the Trail from the Friends Village
- Pavement Cutout Could Be Hazard to Motorists